Previous incidents
ANDE Transmission Event
Created Oct 22 at 08:07am EDT
The ANDE transmission line has had a major transmission event, affecting power delivery to the entire site. Operations are bringing the fleet back up. Normal service should return within a few hours.
ANDE Utility - Mandatory Curtailment - ~6 hours
Resolved Oct 17 at 03:56am EDT
The curtailment commenced at 10:57 hours (GMT -3) and concluded at 14:22 hours (GMT -3). We are pleased to inform you that production across the project has been fully restored to normal.
This curtailment lasted for 3 hours and 25 minutes.
1 previous update
Transformer Maintenance Impacting Rigs
Resolved Sep 26 at 01:55pm EDT
We’re currently observing transformer maintenance, which is causing some rigs to go temporarily offline. Our team is actively monitoring the situation and will provide updates as soon as maintenance is completed.
Scheduled Maintenance
Resolved Sep 08 at 09:57am EDT
All miners are now back online and operating normally. Monitoring shows stable performance across the fleet
1 previous update
Paraguay Air-Cooled Pods under maintenance
Resolved Aug 26 at 01:08pm EDT
General electrical maintenance is being performed. Pods Z1 and Z2 should be back in service in a few hours.
3 of 4 Dams are producing power
Updated Oct 22 at 08:17am EDT
3 of 4 Dams are producing power. Curtailment impacting Wisconsin site.
4 previous updates
Low River Flows - Minor Curtailment
Resolved Aug 15 at 02:23pm EDT
US-WI is under 10% curtailment due to low river flows affecting power production by the dam.
Paraguay site is currently down
Resolved Aug 14 at 06:03am EDT
There has been an interruption in the ANDE transmission line