Paraguay - Curtailment
Resolved
Sep 28, 2026 at 4:17pm UTC
Following our previous communication, we would like to provide additional
details regarding the power consumption regulation requested by ANDE.
They instructed us to curtail part of our production, which was fully
implemented.
ANDE explained that this request was made due to operational restrictions.
The reduction requests from ANDE were carried out in three stages in
accordance with their requirements:
First Curtailment Stage:
ANDE contacted us at 10:35 (GMT-3) via WhatsApp message to request the
first reduction.
This curtailment started on September 28, 2026, at 10:51 (GMT-3) and
concluded on September 28, 2026, at 13:17 (GMT-3). The request was to
reduce 90% of the nominal load, distributed proportionally among all
clients. The curtailment lasted a total of 2 hours and 26 minutes.
Second Curtailment Stage:
ANDE contacted us at 14:15 (GMT-3) via WhatsApp message for the second
reduction request.
This curtailment started on September 28, 2026, at 14:27 (GMT-3) and
concluded on September 28, 2026, at 16:56 (GMT-3). The request was for a 10
MW reduction, distributed proportionally among all clients. The curtailment
lasted a total of 2 hours and 29 minutes.
Third Curtailment Stage:
ANDE contacted us at 19:04 (GMT-3) via WhatsApp message for the third
reduction request.
This curtailment started on September 28, 2026, at 19:10 (GMT-3) and
concluded on September 28, 2026, at 23:05 (GMT-3). The request was for a 30
MW reduction implemented in two phases, distributed proportionally among
all clients. The curtailment lasted a total of 3 hours and 55 minutes.
We are pleased to inform you that production across the project has been
fully restored and is now operating normally.
We apologize for any inconvenience this may have caused and thank you for
your understanding.
Affected services
Created
Sep 28, 2026 at 1:51pm UTC
Following our previous communication, we would like to provide additional
details regarding the power consumption regulation requested by ANDE.
They instructed us to curtail part of our production, which was fully
implemented.
ANDE explained that this request was made due to operational restrictions.
The reduction requests from ANDE were carried out in three stages in
accordance with their requirements:
First Curtailment Stage:
ANDE contacted us at 10:35 (GMT-3) via WhatsApp message to request the
first reduction.
This curtailment started on September 28, 2026, at 10:51 (GMT-3) and
concluded on September 28, 2026, at 13:17 (GMT-3). The request was to
reduce 90% of the nominal load, distributed proportionally among all
clients. The curtailment lasted a total of 2 hours and 26 minutes.
Second Curtailment Stage:
ANDE contacted us at 14:15 (GMT-3) via WhatsApp message for the second
reduction request.
This curtailment started on September 28, 2026, at 14:27 (GMT-3) and
concluded on September 28, 2026, at 16:56 (GMT-3). The request was for a 10
MW reduction, distributed proportionally among all clients. The curtailment
lasted a total of 2 hours and 29 minutes.
Third Curtailment Stage:
ANDE contacted us at 19:04 (GMT-3) via WhatsApp message for the third
reduction request.
This curtailment started on September 28, 2026, at 19:10 (GMT-3) and
concluded on September 28, 2026, at 23:05 (GMT-3). The request was for a 30
MW reduction implemented in two phases, distributed proportionally among
all clients. The curtailment lasted a total of 3 hours and 55 minutes.
We are pleased to inform you that production across the project has been
fully restored and is now operating normally.
We apologize for any inconvenience this may have caused and thank you for
your understanding.
Affected services