Previous incidents
Norway - Curtailment
Resolved Feb 25, 2026 at 12:39pm UTC
Mine back to normal operations.
1 previous update
ANDE Utility Curtailment - extreme heat
Resolved Feb 20, 2026 at 3:24pm UTC
The curtailment commenced on February 16, at 10:35 hours (GMT -3), and concluded on February 19, at 08:33 hours (GMT -3). On February 18, ANDE specifically requested a full modulation due to an overload on its high-voltage transmission line.
We are pleased to inform you that production across the project has been fully restored to normal.
This curtailment lasted for 69 hours and 58 minutes.
Thank you once again for your patience and understanding.
1 previous update
Temporary Consumption Reduction - Container Z1
Resolved Feb 4, 2026 at 11:10am UTC
We would like to inform you that container Z1 is temporarily out of service due to scheduled general maintenance activities.
This event began at 07:30 on February 4, 2026 (GMT -3).
Production will be restored as soon as the maintenance work is completed.
ANDE curtailment request
Resolved Feb 3, 2026 at 1:28pm UTC
We would like to inform you that ANDE has requested a new consumption reduction, which will be implemented shortly.
Further updates regarding this operation will be provided once the reduction process has been completed.
ANDE Utility Curtailment
Resolved Jan 26, 2026 at 2:55pm UTC
We would like to inform you that ANDE has requested a new consumption reduction, which will be implemented shortly.
Further updates regarding this operation will be provided once the reduction process has been completed.
ANDE Utility Curtailement 89% Curtailment - 6 hours
Resolved Jan 24, 2026 at 4:26pm UTC
ANDE instructed us to reduce part of the production, which has already been implemented. According to ANDE, this request was made due to an overload on the 220 kV MD–PIH transmission line.
They contacted us today at 10:18 (GMT -3) via WhatsApp message, approximately 13 minutes before the requested curtailment. As usual, no official email notification was received.
The curtailment started at 10:31 (GMT -3), and the total reduction requested was 89 MW, distributed proportionally among all cli...
Norway - Curtailment
Resolved Feb 16, 2026 at 11:47am UTC
Following our earlier notifications regarding reduced work levels and ongoing curtailment, please be advised that curtailment has been lifted.
We have started the startup of the entire farm now, and ramp-up to full operation is currently in progress.
We will continue to monitor the situation and will advise if any issues arise.
1 previous update
PY-HR ANDE Load Shedding
Resolved Jan 16, 2026 at 2:18pm UTC
ANDE has has implemented load shedding due to high energy demand on transmission lines.
Curtailment
Resolved Jan 15, 2026 at 7:45am UTC
Norway grid is currently under heavy utilization and curtailment has been scheduled for the next few hours. An update will be provided as soon as operations are resumed.
Operations have been resumed.
Hydro container B12 in maintenance
Resolved Jan 14, 2026 at 3:05pm UTC
We would like to inform you that container B12 is temporarily out of service due to scheduled firmware updates and general maintenance activities.
We are pleased to inform you that the consumption levels for container B12 have been fully restored to normal.
The event began on January 14, 2026, at 07:19 (GMT -3) and concluded at 16:24 (GMT -3), with a total duration of 9 hours and 5 minutes.
The restoration of container B12 took longer than initially expected due to additional consumpt...
Container B22 in maintenance
Resolved Jan 13, 2026 at 11:45am UTC
We would like to inform you that container B22 is temporarily out of service due to scheduled firmware updates and general maintenance activities.
This event began at
ANDE Utility Curtailement - reduced load
Resolved Jan 12, 2026 at 3:34pm UTC
The power utility, ANDE, has initiated a curtailment due to grid congestion. Estimated duration is 5 hours.
We are pleased to inform you that the consumption levels have been restored to normal.
All Dams are offline.
Resolved Dec 29, 2025 at 9:37pm UTC
Outage due to blizzard conditions.
1 previous update
ANDE Utility Curtailement - reduced load
Resolved Dec 19, 2025 at 6:04pm UTC
We would like to inform you that ANDE has requested a new consumption reduction, which will be implemented shortly.
Further updates regarding this operation will be provided once the reduction process has been completed.
ANDE Utility Curtailement - reduced load
Resolved Dec 15, 2025 at 7:08pm UTC
They have instructed us to stop part of the production, which has already been implemented. ANDE explained that this request was made due to the following reason: overload on the 220 kV MD–PIH transmission line.
This curtailment started at 13:26 AM (GMT -3), and the reduction request was for 30 MW, distributed proportionally among all clients. The curtailment is expected to last approximately 5 hours, as indicated by ANDE.