ANDE Utility Curtailement - reduced load

Dec 15 at 02:08pm EST
Affected services
Paraguay Air
Paraguay Hydro

Resolved
Dec 15 at 02:08pm EST

They have instructed us to stop part of the production, which has already been implemented. ANDE explained that this request was made due to the following reason: overload on the 220 kV MD–PIH transmission line.

This curtailment started at 13:26 AM (GMT -3), and the reduction request was for 30 MW, distributed proportionally among all clients. The curtailment is expected to last approximately 5 hours, as indicated by ANDE.