September 2026
Sep 19, 2026
1 incident

Texas - Curtailment

Resolved

Resolved Sep 20, 2026 at 12:33am UTC

The Texas site is now exiting curtailment and energizing.

1 previous update

Sep 17, 2026
2 incidents

Texas - Curtailment

Resolved

Resolved Sep 18, 2026 at 1:29am UTC

The Texas site is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Sep 18, 2026 at 1:18am UTC

The Texas site is now exiting curtailment and energizing.

1 previous update

Sep 16, 2026
6 incidents

Texas - Curtailment

Resolved

Resolved Sep 17, 2026 at 2:04am UTC

The Texas site is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Sep 17, 2026 at 12:40am UTC

The Texas site is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Sep 17, 2026 at 12:30am UTC

The Texas site is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Sep 17, 2026 at 12:20am UTC

The Texas site is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Sep 16, 2026 at 11:02pm UTC

The Texas site is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Sep 16, 2026 at 8:04pm UTC

The Texas site is now exiting curtailment and energizing.

1 previous update

Sep 15, 2026
2 incidents

Texas - Curtailment

Resolved

Resolved Sep 15, 2026 at 11:17pm UTC

The Texas site is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Sep 15, 2026 at 9:35pm UTC

The Texas site is now exiting curtailment and energizing.

1 previous update

Sep 14, 2026
2 incidents

Norway - Curtailment

Resolved

Resolved Sep 15, 2026 at 7:00am UTC

Іnform you that electricity prices have dropped and we've launched the miners. Miners are now reaching their target capacity.

1 previous update

Texas - Curtailment

Resolved

Resolved Sep 14, 2026 at 11:47pm UTC

The Texas site is now exiting curtailment and energizing.

1 previous update

Sep 13, 2026
1 incident

Texas - Curtailment

Resolved

Resolved Sep 13, 2026 at 11:10pm UTC

The Texas site is now exiting curtailment and energizing.

1 previous update

Sep 12, 2026
1 incident

Texas - Curtailment

Resolved

Resolved Sep 12, 2026 at 11:47pm UTC

The Texas site is now exiting curtailment and energizing.

1 previous update

Sep 11, 2026
2 incidents

Texas - Curtailment

Resolved

Resolved Sep 11, 2026 at 10:11pm UTC

The Texas site is now exiting curtailment and energizing.

1 previous update

Paraguay - Maintenance

Resolved

Resolved Sep 11, 2026 at 7:21pm UTC

We would like to inform you that containers B12, B22, B32, D22, T32, T42, Z1, Z2, and Z3 were temporarily out of service due to an incident: an ANDE 220 kV transmission line outage caused by the activation of overvoltage protection.

The event, which began at 13:47 hours (GMT -3), ended at 16:21 hours (GMT -3) and lasted 2 hours and 34 minutes. Production has now returned to its standard levels.

1 previous update

Sep 10, 2026
4 incidents

Texas - Curtailment

Resolved

Resolved Sep 10, 2026 at 11:43pm UTC

The Texas site is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Sep 10, 2026 at 11:32pm UTC

The Texas site is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Sep 10, 2026 at 11:22pm UTC

The Texas site is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Sep 10, 2026 at 11:12pm UTC

The Texas site is now exiting curtailment and energizing.

1 previous update

Sep 09, 2026
1 incident

Texas - Curtailment

Resolved

Resolved Sep 9, 2026 at 10:41pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Sep 08, 2026
3 incidents

Norway - Curtailment

Resolved

Resolved Sep 10, 2026 at 8:27am UTC

All rigs are powering back up after curtailment.

1 previous update

Texas - Curtailment

Resolved

Resolved Sep 9, 2026 at 2:49am UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Sep 8, 2026 at 11:47pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Sep 07, 2026
1 incident

Texas - Curtailment

Resolved

Resolved Sep 7, 2026 at 11:57pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Sep 06, 2026
1 incident

Norway - Curtailment

Resolved

Resolved Sep 7, 2026 at 5:30am UTC

Please note that high prices are forecasted for tomorrow (7 September 2026). To optimize costs, the operations will be reduced.

Start time: 5:45 CET
End time: 7:30 CET

1 previous update

Sep 05, 2026
1 incident

Paraguay - Overvoltage

Resolved

Resolved Sep 5, 2026 at 10:58am UTC

We would like to inform you that containers D22 and Z2 were temporarily affected by an overvoltage event on the 220 kV MD–PIH transmission line.

The event began on September 05, 2026, at 06:26 (GMT -3) and concluded on September 05, 2026, at 07:58 (GMT -3), with a total duration of 1 hour and 31 minutes.

We are pleased to confirm that the event has been fully resolved and that containers D22 and Z2 are now operating normally. Production has returned to standard levels.

1 previous update

Sep 02, 2026
2 incidents

Texas - Curtailment

Resolved

Resolved Sep 3, 2026 at 2:35am UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Sep 2, 2026 at 11:47pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Sep 01, 2026
3 incidents

Texas - Curtailment

Resolved

Resolved Sep 2, 2026 at 1:49am UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Sep 2, 2026 at 12:01am UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Norway - Curtailment

Resolved

Resolved Sep 1, 2026 at 12:00pm UTC

Please note that high prices are forecasted for tomorrow (1 September 2026). To optimize costs, we plan to reduce operations during the following periods (local time):

6:15 — 10:15
10:45 — 11:00
11:45 — 12:15
12:45 — 13:45

1 previous update

August 2026
Aug 30, 2026
1 incident

Texas - Curtailment

Resolved

Resolved Aug 31, 2026 at 1:35am UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Aug 28, 2026
2 incidents

Paraguay - Maintenance

Resolved

Resolved Aug 28, 2026 at 3:51pm UTC

Greetings Sirs,

I hope this message finds you well.

We are pleased to inform you that the consumption levels for container B22 have been restored to normal.

The modulation event, which began on August 28, 2026, at 10:10 hours (GMT -3), ended on August 28, 2026, at 12:51 hours (GMT -3) and lasted 2 hours and 41 minutes. Production has now returned to its standard levels.

Best regards,

1 previous update

Paraguay - Maintenance

Resolved

Resolved Aug 28, 2026 at 1:07pm UTC

We are pleased to inform you that the consumption levels for Container D22 have been restored to normal.

The modulation event, which began at 07:57 hours (GMT -3), ended at 10:07 hours (GMT -3) and lasted 02 hour 10 minutes. Production has now returned to its standard levels.

1 previous update

Aug 27, 2026
2 incidents

Texas - Curtailment

Resolved

Resolved Aug 27, 2026 at 10:11pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Aug 27, 2026 at 9:11pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Aug 26, 2026
5 incidents

Texas - Curtailment

Resolved

Resolved Aug 27, 2026 at 4:19am UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Aug 26, 2026 at 11:19pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Aug 26, 2026 at 10:57pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Aug 26, 2026 at 12:48pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Paraguay - Maintenance

Resolved

Resolved Aug 26, 2026 at 11:14am UTC

We would like to inform you that Container B32 temporarily out of service due to scheduled maintenance.

This event began at 08:14 hours (GMT -3) and is expected to last approximately 4 hours. Production will be restored as soon as possible.

1 previous update

Aug 25, 2026
2 incidents

Paraguay - Maintenance

Resolved

Resolved Aug 26, 2026 at 2:18am UTC

The event began on August 25, 2026, at 22:57 (GMT-3) and concluded at 23:18 (GMT-3), with a total duration of 21 minutes.

1 previous update

Texas - Curtailment

Resolved

Resolved Aug 25, 2026 at 10:46pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Aug 24, 2026
2 incidents

Texas - Curtailment

Resolved

Resolved Aug 25, 2026 at 12:01am UTC

Dorothy_AC002: Project Dorothy has been curtailed due to the requirement to draw power exclusively from the wind farm in compliance with the Utilities' Curtailment Rules [4CP or Grid Prices], but there is not enough wind at the moment.

1 previous update

Paraguay - Maintenance

Resolved

Resolved Aug 24, 2026 at 3:13pm UTC

The modulation event, which began at 07:56 hours (GMT -3), ended at 12:13 hours (GMT -3) and lasted 4 hours and 17 minutes.

1 previous update

Aug 23, 2026
2 incidents

Texas - Curtailment

Resolved

Resolved Aug 24, 2026 at 3:06am UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Aug 23, 2026 at 11:56pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Aug 22, 2026
3 incidents

Texas - Curtailment

Resolved

Resolved Aug 23, 2026 at 5:03am UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Aug 22, 2026 at 11:41pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Aug 22, 2026 at 9:26pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Aug 21, 2026
2 incidents

Texas - Curtailment

Resolved

Resolved Aug 21, 2026 at 10:56pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Aug 21, 2026 at 9:11pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Aug 20, 2026
1 incident

Texas - Curtailment

Resolved

Resolved Aug 21, 2026 at 12:11am UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Aug 19, 2026
2 incidents

Texas - Curtailment

Resolved

Resolved Aug 19, 2026 at 11:56pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Paraguay - Maintenance

Resolved

Resolved Aug 19, 2026 at 6:36pm UTC

We would like to inform you that Container Z1 is temporarily out of service due to transformer rotation work.

The modulation event, which began on August 19, 2026, at 08:00 (GMT-3), ended on August 19, 2026, at 15:36 (GMT-3) and lasted 7 hours and 36 minutes.

1 previous update

Aug 18, 2026
3 incidents

Norway - Curtailment

Resolved

Resolved Aug 22, 2026 at 3:51pm UTC

The site is currently operating at full capacity

1 previous update

Texas - Curtailment

Resolved

Resolved Aug 19, 2026 at 1:19am UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Aug 19, 2026 at 12:12am UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Aug 17, 2026
2 incidents

Texas - Curtailment

Resolved

Resolved Aug 18, 2026 at 2:34am UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Aug 17, 2026 at 11:42pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Aug 16, 2026
1 incident

Texas - Curtailment

Resolved

Resolved Aug 16, 2026 at 11:41pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Aug 15, 2026
1 incident

Texas - Curtailment

Resolved

Resolved Aug 15, 2026 at 11:41pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Aug 14, 2026
2 incidents

Texas - Curtailment

Resolved

Resolved Aug 14, 2026 at 10:56pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Paraguay - Maintenance

Resolved

Resolved Aug 14, 2026 at 3:04pm UTC

We would like to inform you that container D22 was temporarily out of service due to an electrical system issue that caused the main circuit breaker (TM) to trip.

This event began at 11:27 hours (GMT -3) and concluded at 12:04 hours (GMT -3), with a total duration of 37 minutes.

1 previous update

Aug 13, 2026
3 incidents

Texas - Curtailment

Resolved

Resolved Aug 13, 2026 at 11:22pm UTC

Dorothy_AC002: Project Dorothy has been curtailed due to the requirement to draw power exclusively from the wind farm in compliance with the Utilities' Curtailment Rules [4CP or Grid Prices], but there is not enough wind at the moment.

1 previous update

Paraguay - Maintenance

Resolved

Resolved Aug 13, 2026 at 6:17pm UTC

We would like to inform you that container B12 was temporarily operating at reduced production due to a failure of the cooling system is now Resolved

1 previous update

Paraguay - Maintenance

Resolved

Resolved Aug 13, 2026 at 5:36am UTC

We would like to inform you that container Z3, racks 4, 5, 6, and 7 were temporarily out of service due to an electrical system issue that caused the main circuit breaker (TM) to trip.

This event began at 01:22 hours (GMT -3) and concluded at 02:36 hours (GMT -3), with a total duration of 1 hour and 14 minutes.

1 previous update

Aug 12, 2026
1 incident

Texas - Curtailment

Resolved

Resolved Aug 13, 2026 at 12:17am UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Aug 11, 2026
1 incident

Texas - Curtailment

Resolved

Resolved Aug 12, 2026 at 12:11am UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Aug 07, 2026
1 incident

Texas - Curtailment

Resolved

Resolved Aug 7, 2026 at 10:26pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Aug 06, 2026
2 incidents

Texas - Curtailment

Resolved

Resolved Aug 6, 2026 at 11:12pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Texas - Curtailment

Resolved

Resolved Aug 6, 2026 at 11:01pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Aug 05, 2026
1 incident

Texas - Curtailment

Resolved

Resolved Aug 5, 2026 at 11:56pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Aug 04, 2026
1 incident

Texas - Curtailment

Resolved

Resolved Aug 5, 2026 at 12:13am UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Aug 03, 2026
1 incident

Texas - Curtailment

Resolved

Resolved Aug 4, 2026 at 12:10am UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Aug 02, 2026
1 incident

Texas - Curtailment

Resolved

Resolved Aug 2, 2026 at 11:31pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Aug 01, 2026
1 incident

Texas - Curtailment

Resolved

Resolved Aug 1, 2026 at 11:11pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

July 2026
Jul 30, 2026
1 incident

Texas - Curtailment

Resolved

Resolved Jul 30, 2026 at 11:01pm UTC

Dorothy_EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Jul 26, 2026
1 incident

Paraguay - Curtailment

Resolved

Resolved Jul 27, 2026 at 1:20am UTC

ANDE instructed us to partially stop production, which was implemented as requested. The reason provided by ANDE was: overload on the LI-220 kV PIH-MD line.

They contacted us on July 26, 2026, at 18:35 (GMT -3) via WhatsApp message, approximately 18 minutes before the requested curtailment began. As usual, no email notification was received.

The curtailment began on July 26, 2026, at 18:53 (GMT -3) and concluded at 22:20 (GMT -3), lasting a total of 3 hours and 27 minutes.

1 previous update

Jul 24, 2026
1 incident

Paraguay - Curtailment

Resolved

Resolved Jul 27, 2026 at 11:40pm UTC

ANDE instructed us to partially stop production, which was implemented as requested. The reason provided by ANDE was: overload on the LI-220 kV PIH-MD line.

They contacted us on July 24, 2026, at 17:18 (GMT -3) via WhatsApp message, approximately 1 hour and 2 minutes before the requested curtailment began. As usual, no email notification was received.

The curtailment began on July 24, 2026, at 18:20 (GMT -3) and concluded at 20:40 (GMT -3), lasting a total of 2 hours and 20 minutes.

1 previous update

Jul 22, 2026
3 incidents

Texas - Curtailment

Resolved

Resolved Jul 23, 2026 at 4:04am UTC

EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Paraguay - Power Outage

Resolved

Resolved Jul 22, 2026 at 8:07am UTC

the containers (D22, Z1, Z2, and Z3) were temporarily out of service due to an overvoltage event on the LT-500 VHA-VAL-AYO transmission line.

The event began on July 22, 2026, at 01:24 (GMT -3) and concluded on July 22, 2026, at 05:07 (GMT -3), with a total duration of 3 hours and 43 minutes.

1 previous update

Norway - Planned Maintenance

Resolved

Resolved Jul 22, 2026 at 7:00am UTC

this only applies to skid1

1 previous update

Jul 21, 2026
1 incident

Texas - Curtailment

Resolved

Resolved Jul 22, 2026 at 3:50am UTC

EC007: Project Dorothy is now exiting curtailment and energizing.

1 previous update

Jul 20, 2026
1 incident

Texas - Curtailment

Resolved

Resolved Jul 21, 2026 at 1:48am UTC

Project Dorothy is now exiting curtailment and energizing.

1 previous update

Jul 19, 2026
1 incident

Texas - Curtailment

Resolved

Resolved Jul 19, 2026 at 11:26pm UTC

4CP Curtailment ended

1 previous update

Jul 17, 2026
1 incident

Norway - Planned Maintenance

Resolved

Resolved Jul 17, 2026 at 10:31am UTC

Norway - [Planned Maintenance] is complete at 12:30 local time.

1 previous update

Jul 10, 2026
2 incidents

Norway - Maintenance

Resolved

Resolved Jul 13, 2026 at 2:26pm UTC

Resolved

1 previous update

South Dakota - Utility Provider Issues

Resolved

Resolved Jul 13, 2026 at 7:57am UTC

The utility provider issues have been resolved, mine is back online.

1 previous update

Jul 01, 2026
1 incident

4CP 1st of the month curtailment

Resolved

Resolved Jul 2, 2026 at 12:00am UTC

Curtailment has finished and mining operations are gradually getting back to full capacity.

1 previous update