Paraguay - Curtailment
Resolved
Nov 14, 2026 at 1:31am UTC
Following our previous communication, we would like to provide full details
regarding the consumption regulation requested by ANDE.
ANDE instructed us to partially stop production, which was implemented as
requested. The reason provided by ANDE was: overload on the LI-220 kV
PIH-MD line.
They contacted us on November 13, 2026, at 10:50 (GMT -3) via WhatsApp
message, approximately 6 minutes before the requested curtailment began. As
usual, no email notification was received.
The curtailment began on November 13, 2026, at 10:56 (GMT -3) and concluded
at 22:31 (GMT -3), lasting a total of 11 hours and 35 minutes.
During this period, ANDE requested several production reductions, totaling
40 MW, distributed proportionally among all clients.
We are pleased to confirm that production across the project has been fully
restored and operations have returned to normal levels.
We apologize for any inconvenience and thank you for your understanding.
Affected services
Created
Nov 13, 2026 at 1:56pm UTC
Following our previous communication, we would like to provide full details
regarding the consumption regulation requested by ANDE.
ANDE instructed us to partially stop production, which was implemented as
requested. The reason provided by ANDE was: overload on the LI-220 kV
PIH-MD line.
They contacted us on November 13, 2026, at 10:50 (GMT -3) via WhatsApp
message, approximately 6 minutes before the requested curtailment began. As
usual, no email notification was received.
The curtailment began on November 13, 2026, at 10:56 (GMT -3) and concluded
at 22:31 (GMT -3), lasting a total of 11 hours and 35 minutes.
During this period, ANDE requested several production reductions, totaling
40 MW, distributed proportionally among all clients.
We are pleased to confirm that production across the project has been fully
restored and operations have returned to normal levels.
We apologize for any inconvenience and thank you for your understanding.
Affected services